Winter hydropower: Moiry dam-raising project makes progress

11/17/2026, 09:00 | News

Sierre – The project to raise the Moiry dam will increase the availability of hydropower in winter, helping to strengthen Switzerland’s security of supply. Technical studies for the construction project are under way, with the next steps involving the preparation of the documentation required for the approval procedures. Various environmental compensation measures have been explored during meetings and site visits with environmental organisations. The project planning also takes account of access routes, sustainable mobility and tourism activities, as well as the needs of businesses and visitors to the area. Visitor facilities will also be redesigned, including the relocation of the existing restaurant to make way for the dam-raising works.

Forces Motrices de la Gougra SA (FMG) plans to raise the Moiry dam by nine metres. The additional storage capacity will make it possible to shift part of the electricity generation from summer to the winter months, when demand is high. The project also requires advance planning of changes to access routes and infrastructure, while ensuring the site can continue to accommodate different activities and visitors to the site. The Moiry dam-raising project is among the hydropower projects agreed upon in 2021 by representatives of the Swiss Confederation, cantons, energy sector and environmental organisations as part of the Hydropower Round Table. It is therefore one of the 16 expansion projects included in the Federal Act on a Secure Electricity Supply from Renewable Energy Sources.

New access routes and visitor infrastructure

The Moiry dam is an important tourist attraction in the Val d’Anniviers. Raising the dam provides an opportunity to rethink visitor facilities and the layout of the site. At the municipal assembly on 16 November, the municipality of Anniviers presented its plans for access routes and tourism infrastructure, along with an update on the project’s overall progress, to local residents. The existing restaurant will need to be relocated, and discussions are under way with its owner and the municipality to find a solution. The details will be worked out with the relevant partners.

The Moiry dam is part of the identity of the Val d’Anniviers. The project must contribute to Switzerland’s energy supply while also taking account of the future of this much-loved site for local residents and visitors. It is essential that these developments form part of a long-term vision.

David Melly, President of the municipality of Anniviers

More storage capacity for winter

Raising the dam will increase the storage capacity of Lake Moiry by approximately 15%, equivalent to more than 12 million cubic metres. This will make it possible to shift around 50 GWh of energy from summer to winter. There are also plans to increase the pumping capacity between the Mottec power station and Moiry. Together, these two measures will allow more flexible operation of the hydropower facilities.

The Moiry dam plays an important role in Switzerland’s electricity supply. By raising it and increasing pumping capacity, we will generate more electricity in winter, when the country needs it most. This project is a clear example of the contribution that hydropower can make to Switzerland.

Michaël Plaschy, Chairman of the Board of Directors of Forces Motrices de la Gougra SA

Next steps

Technical studies for the construction project are under way and are expected to be completed in early 2027. FMG is already preparing the documentation required for the approval procedures. The executive authorities of the concession-granting municipalities confirmed their support for the project at the end of 2025. Discussions with environmental organisations and the authorities on compensation and additional measures are ongoing (see box). Subject to the successful completion of all the necessary procedures, construction work is scheduled to begin in 2029.

Environmental measures developed through collaboration

FMG is working with the environmental organisations concerned to develop measures to compensate for the environmental impacts of raising the dam. During site visits, various locations and potential measures in the region have been examined to assess their suitability. Discussions also cover additional measures required for all projects included in the Swiss Confederation’s Hydropower Round Table. FMG is continuing this dialogue with the aim of developing and agreeing on a package of measures tailored to the project that will deliver lasting benefits for the region’s natural environment.


For further information, visit Gougra power plant