EN |DE |FR |IT
  • Home
  • Contact

    Group Contacts

    Operational Headquarters

    Alpiq Holding AG

    Bahnhofquai 12

    4601 Olten

    Switzerland

    T: +41 62 286 71 11

    F: +41 62 286 73 73

    info@­alpiq.­com

    www.alpiq.com

    Energy International

    Reinhold Frank

    Alpiq Holding Ltd.

    Head of Energy International

    T: +41 62 286 74 66

    F: +41 62 286 71 30

    Energy Switzerland

    Michael Wider

    Alpiq Suisse SA

    Head of Energy Switzerland

    Ch. de Mornex 10 / CP 570

    1001 Lausanne

    Switzerland

    T: +41 21 341 21 11

    info.­lausanne@­alpiq.­com

    Optimisation & Trading

    Erik Saether

    Alpiq Trading AG

    Head of Optimisation & Trading a.i.

    Bahnhofquai 12

    4601 Olten

    Switzerland

    T: +41 62 286 71 11

    info.­trading@­alpiq.­com


  • Sitemap
  • Login
Alpiq in: Europe

Lavorgo - Mettlen

Lavorgo-Mettlen grid construction works

Section of the 380-kV high-voltage Lavorgo-Mettlen power line to be renovated

This summer Alpiq Grid Ltd. Gösgen is planning to replace 28 supports for the existing Lavorgo-Mettlen power line on the section between Arth and Küssnacht am Rigi, along the north flank of the Rigi. Work will start in early May and is scheduled for completion at the end of October 2008. The cost of replacing the pylons will be around CHF 15 million.

Renovation work on the 380-kV line, on the 8.5-kilometer long section in the canton of Schwyz between Arth and Küssnacht am Rigi, is part of the overall upgrade of the power line between Amsteg and Mettlen. All pylons along the line, which is more than 60 years old, will be replaced by new supports. The line axis remains unchanged. At an average height of 64 meters, the new supports will be somewhat taller than the old pylons. This will achieve two objectives: The greater distance from the ground and buildings will offer better protection against non-ionising radiation. And the higher pylons will improve the operational reliability of the 380-KV line. Operational reliability is particularly important since the line is an essential element on the North-South axis of the Swiss transmission grid. The line will make an important contribution to energy supplies in central Switzerland.

Plans for renovation were officially published in the spring of 2002. Alpiq Grid Ltd. made several modifications in response to various appeals and concerns. The plans to renovate the line section were approved by the Swiss Federal Office for Energy in March 2008, and construction began on 5 May 2008. During the construction work from mid-May to the end of October 2008, the 380-kV Lavorgo-Mettlen line will be temporarily routed via the parallel power line operated by CKW. The cost of replacing the pylons will be around CHF 15 million.

The 380-kV power line between Lavorgo and Mettlen was first built in 1948/49. Despite extensive maintenance since then, corrosion and ageing have now reached the point where the pylons need to be replaced. Alpiq Grid Ltd. Gösgen is implementing the replacement project in phases. The first phase was launched in 1989, and in the summer of 2006 the company replaced 17 supports between Sisikon and Ingenbohl. Over the next few years the supports on both sections of Ingenbohl and Arth in the canton of Schwyz, as well as the section between Küssnacht am Rigi and Udligenswil in the canton of Lucerne, will be replaced.

New electricity pylons on the north flank of the Rigi

This summer Atel Transmission Ltd. is planning to replace 28 supports for the existing Lavorgo-Mettlen power line on the section between Arth and Küssnacht am Rigi, along the north flank of the Rigi. Work will start in early May and is scheduled for completion at the end of October 2008. The cost of replacing the pylons will be around CHF 15 million.

380 kV

Switzerland

Lavorgo - Mettlen, Switzerland

Alpiq owned