EN |DE |FR |IT
  • Home
  • Contact

    Group Contacts

    Headquarters

    Alpiq Holding Ltd.

    Ch. de Mornex 10

    1003 Lausanne

    Switzerland

    T: +41 21 341 21 11

    info@­alpiq.­com

    www.alpiq.com

    Energy Services

    Reinhold Frank

    Alpiq Holding Ltd.

    Head of Energy Services

    T: +41 62 286 74 66

    F: +41 62 286 71 30

    Generation

    Michael Wider

    Alpiq Suisse SA

    Head of Generation

    Ch. de Mornex 10 / CP 570

    1001 Lausanne

    Switzerland

    T: +41 21 341 21 11

    info.­lausanne@­alpiq.­com

    Commerce & Trading

    Erik Saether

    Alpiq Ltd.

    Head of Commerce & Trading a.i.

    Bahnhofquai 12

    4601 Olten

    Switzerland

    T: +41 62 286 71 11

    info.­trading@­alpiq.­com

  • Sitemap
  • Login
Alpiq in: Europe

Energy security

News: 31.01.2013 09:30

Alpiq sees serious gaps in the 2050 energy strategy

Bundeshaus, Bern

Alpiq acknowledges the fact that Switzerland’s energy system needs to be comprehensively transformed until 2050, and assumes that the Swiss people will be allowed to vote on this transformation at a given point in time. Alpiq further assumes that the political considerations are predicated on the electricity industry’s legal service provision ...

News: 04.01.2013 11:00

Alpiq transfers its ultra-high-voltage grid to Swissgrid

Mast Gösgen

Swissgrid now owns the 1,800 kilometres of UHV power lines that up to now were the property of Alpiq. As part of the transaction, Swissgrid also assumes responsibility for continuing the high-priority plans to expand the transmission system.

News: 29.08.2012 15:30

Chamoson – Chippis ultra-high voltage line: a landmark decision

Mastenbau

The Federal Administrative Court has today confirmed planning approval for the ultra-high voltage overhead line between Chamoson and Chippis. The application for laying the line underground was rejected. For Alpiq this is an important step. Top priority is accorded to construction of the 380-kV line by 2015.

News: 11.07.2012 11:30

The largest hydroelectric construction project in Valais enters a new, major phase

Emosson

Almost two years after arriving in Châtelard (Valais), tunnel workers prepare to cut through the last metres of the access tunnel to the future pumped storage power plant of Nant de Drance. This stage, which is on the verge of being completed, is all-important for Alpiq, the CFF and the Forces Motrices Valaisannes (FMV) – the three partners that ...

News: 21.09.2011 10:30

Alpiq starts up modernised Lavorgo switching station

Lavorgo switching station

Following work to modernise the Lavorgo substation in canton Ticino, Alpiq celebrated the start-up with an official inauguration on 20 September 2011. The new 380-/220-kV switching station plays an important role in Switzerland's transmission grid, by connecting the canton of Ticino with communities north of the Alps as well as the North-South ...

News: 25.05.2011 17:30

The main focus must be on energy security

Bundeshaus, Bern

Alpiq takes note of the Federal Council's decision. Coupled with the parliamentary motions submitted and the people's initiatives which have been announced, this decision will usher in a political process, lasting many years, to change the constitution and/or existing legislation. During this time a large number of issues regarding ways of ...

News: 23.04.2010 07:00

Alpiq lodges appeal against ElCom ruling

Pylon

On 22 April 2010, Alpiq lodged an appeal against the ruling issued by the Federal Electricity Commission (ElCom) on 4 March 2010. Alpiq is convinced that there is no legal basis for the additional charges imposed by ElCom in connection with ancillary services. It is now up to the Federal Administrative Court to decide.

News: 10.08.2009 13:30

Anxiety about the risk of an electricity shortage and approval for energy independence

The "Perspectives" opinion survey, commissioned by Alpiq and carried out across the country for the first time in 2009, sheds light on the behaviour, concerns and expectations of Swiss electricity consumers. The respondents spontaneously quote shortage of energy as the main risk for the future. In terms of solutions, they greatly overestimate the ...

News: 23.04.2009 16:00

Alpiq production companies lodge appeals against ElCom ruling

Alpiq Group production companies today lodged appeals with the Federal Administrative Court against the ruling issued by the Federal Electricity Commission (ElCom) on 6 March 2009. The Federal Administrative Court must now examine individual aspects of the ElCom ruling, and in particular the question of whether the costs for services that support ...

News: 06.03.2009 11:00

Cabling of the power supply line Chamoson-Chippis

After several political bodies and private persons had demanded that a cabling of the 380 kV power supply line from Chamoson to Chippis be checked out, Alpiq, or rather EOS, commissioned three companies (amongst them ABB) to prepare offers for underground laying; one for an alternating current (AC) cable and one for a direct current (HVDC Light) ...